* BikeWorks Manager report has pointed to a number of expenses outside of the approved budget. Financial assessment is required before any further expenses are incurred.
* BikeWorks Manager report has pointed to a number of expenses outside of the approved budget. Financial assessment is required before any further expenses are incurred.
* Chris updated the [https://docs.google.com/a/edmontonbikes.ca/spreadsheet/ccc?key=0AiPA_mxTBvz1dDVlallkb3EzMGdNUWZEUTZtWlZYMkE&usp=drive_web#gid=3 Reno Budget]:
** approved budget of $16,500
** actual budget $16,115 but still must complete:
***Doors ~$2,000
***Door installation ~$1,000
***Fencing ~ $850
***Window coverings ?
***Vending machine $7,338